National AI Computing Center: Key Institutions and Roles Explained


National AI Computing Center Overview
The National AI Computing Center began construction in August 2026 at Solasido Enterprise City in Haenam. Led by the Samsung SDS consortium, it is planned to expand to an 80MW capacity by 2030. The center serves as a core infrastructure to strengthen AI capabilities and support domestic AI semiconductor development, earning the nickname 'AI Heart' as South Korea's strategic base for achieving its goal of becoming one of the world's top three AI nations.
By 2028, the center aims to deploy 15,000 GPUs to enhance AI computing capacity and attract 320 AI-related companies to the Gwangju region to boost local industry. The Samsung SDS-led consortium will invest a total of 2.5 trillion won in this project, with Ellis Group responsible for managing the 'GPU Engine' to introduce cutting-edge AI semiconductor technology and address supply shortages.
Key Participating Institutions and Their Roles
The Samsung SDS consortium leads and oversees the National AI Computing Center. This aligns with Samsung SDS's cloud-based AI infrastructure expansion strategy and serves as a key tool for developing domestic AI semiconductors. Samsung SDS, overseeing a 2.5 trillion won national AI infrastructure project, broke ground at the center's groundbreaking ceremony.
Ellis Group is responsible for the 'GPU Engine' of AICA National AI Data Center, introducing the latest AI semiconductor technology to address GPU supply shortages. This supports companies in effectively utilizing high-performance computing resources for AI model development and training.
In Gwangju, 320 AI-related companies have been attracted, leveraging the center's infrastructure to drive regional economic revitalization. The National AI Computing Center is referred to as an 'AI Highway,' laying the groundwork for domestic AI semiconductor development while also exploring collaborations for market entry into South America.
Expansion Plans and Timeline
The National AI Computing Center began construction in August 2026, with plans to deploy 15,000 GPUs by 2028. This represents a strategic goal for expanding AI infrastructure and developing domestic AI semiconductors, with an intended expansion to an 80MW capacity by 2030.
The groundbreaking ceremony took place between August 3-4, 2026, where the Samsung SDS consortium broke ground. By 2028, the deployed GPUs will accelerate AI model development and training, enhancing corporate competitiveness.
By 2030, the expanded center will become a core infrastructure for strengthening South Korea's AI competitiveness in Haenam Solasido Enterprise City. This project exemplifies Samsung SDS-led national AI infrastructure construction efforts.
Strategic Location
Nicknamed the 'AI Heart,' the National AI Computing Center will function as a key foundation for South Korea's goal of becoming one of the world's top three AI nations. Built under Samsung SDS leadership, it connects with 320 AI companies in Gwangju to drive regional economic revitalization.
The location at Haenam Solasido Enterprise City offers excellent infrastructure and transportation, providing an ideal environment for AI technology development and innovation. This strategic site supports domestic AI semiconductor development and enables potential collaborations for market entry into South America.
By 2030, the center will expand to an 80MW capacity, a critical infrastructure for South Korea to compete globally in AI. The expansion, alongside GPU deployment and adoption of cutting-edge AI semiconductor technology, aims to overcome supply shortages.
Key Information to Verify
The construction start date is confirmed as August 2026. Led by the Samsung SDS consortium with a total investment of 2.5 trillion won, the center is located at Haenam Solasido Enterprise City and plans to expand to an 80MW capacity by 2030.
By 2028, 15,000 GPUs will be deployed to support AI infrastructure expansion and domestic AI semiconductor development. Ellis Group manages the 'GPU Engine,' while 320 AI companies in Gwangju are connected with the center to drive economic revitalization.
All information is based on Samsung SDS-led National AI Computing Center construction announcements and official press releases, referenced from sources 1, 2, 3, 8, 12, 14, 16, 18, 20, 21, 23, 24, 26, 27, 29.
Frequently Asked Questions
Which institution leads the National AI Computing Center?
The Samsung SDS consortium leads and oversees the National AI Computing Center. This aligns with Samsung SDS's cloud-based AI infrastructure expansion strategy and serves as a key tool for developing domestic AI semiconductors.
When is the National AI Computing Center expected to be completed?
The center began construction in August 2026, with plans to deploy 15,000 GPUs by 2028. It is scheduled to expand to an 80MW capacity by 2030.
Which companies have been attracted near the National AI Computing Center?
320 AI-related companies have been attracted to Gwangju, leveraging the center's infrastructure to drive regional economic revitalization.
Frequently Asked Questions
The National AI Computing Center is being constructed in Haenam Solasido Enterprise City by the Samsung SDS consortium starting in August 2026. The center will expand to an 80MW capacity by 2030, deploying 15,000 GPUs by 2028 to strengthen AI infrastructure and support domestic AI semiconductor development.
Ellis Group manages the 'GPU Engine,' while 320 AI companies in Gwangju are connected with the center to drive regional economic revitalization. The center is nicknamed the 'AI Heart' and functions as a strategic base for South Korea's goal of becoming one of the world's top three AI nations.
The center will expand by 2030, contributing to strengthening South Korea's global competitiveness in AI. All information is based on official announcements and press releases from Samsung SDS-led National AI Computing Center construction efforts.

You can explore similar articles in one place.
View Related ArticlesFAQ
Which institution leads the National AI Computing Center?
The Samsung SDS consortium leads and oversees the National AI Computing Center. This aligns with Samsung SDS's cloud-based AI infrastructure expansion strategy and serves as a key tool for developing domestic AI semiconductors.
When is the National AI Computing Center expected to be completed?
The center began construction in August 2026, with plans to deploy 15,000 GPUs by 2028. It is scheduled to expand to an 80MW capacity by 2030.
Which companies have been attracted near the National AI Computing Center?
320 AI-related companies have been attracted to Gwangju, leveraging the center's infrastructure to drive regional economic revitalization.