Key Factors in Selecting the Honam Semiconductor Cluster Site
The Selection Process of the Honam Semiconductor Cluster Site
The final site for the Honam semiconductor cluster has been confirmed as the area near Gwangju Military Airport. This decision was made based on factors including power grid infrastructure, water supply availability, and balanced regional development policies. According to a July 6, 2026 report by Shin-A Ilbo, the Blue House officially announced the site location, with Muan County being identified as "the key" to the Honam Semiconductor Mega Fab.

The Selection Process and Controversy
In the selection process, areas near Ramsar wetlands and Mangun-myeon in Muan County were among the main candidates. The government's investment decision has sparked political debate between ruling and opposition parties. A 364-square-kilometer land transaction control zone has been designated to prevent speculation. Representative Yu Seung-min has called for public disclosure of semiconductor investment site criteria, while Rep. Jo Bae-sook argues that the project should be pursued as a national strategy beyond political disputes.
Selection Criteria and Policy Background
The selection of the Honam semiconductor cluster site prioritized power grid infrastructure and water supply. Samsung Electronics and SK Hynix selected a 250,000 pyeong (approximately 824,000 square meters) government-owned land near Gwangju Military Airport as their candidate location, which aligns with policy efforts to address regional disparities in power production. The goal is to complete the ±500kV voltage HVDC and underground power grid by the end of 2029.
The government has applied a priority for non-capital regions in advancing the Honam semiconductor cluster, aiming to begin construction in July 2027 as outlined in a roadmap announced on August 5, 2026. A policy offering up to 100% support for infrastructure costs has been introduced, with the eastern part of South Jeolla Province selected as the cluster location due to its potential for regional balance and infrastructure development.
With Gwangju Military Airport confirmed as the Honam semiconductor cluster site, Muan County has emerged as a key area for the "Honam Semiconductor Mega Fab." However, the People Power Party (PPP) has demanded disclosure of land ownership in Honam and targeted it for special investigation, escalating political tensions.
Power Grid and Water Supply Plans
The power grid construction for the Honam semiconductor cluster is scheduled to be completed by the end of 2029 using ±500kV voltage HVDC and underground methods. This aims to resolve regional disparities in power production and boost local economic activity. Water supply availability was also a critical factor in site selection.
A 364-square-kilometer land transaction control zone was established on July 11, 2026, to prevent speculation. Reports about the Ramsar wetland variable began on August 19, 2026, and Muan Mangun-myeon was officially confirmed as the Gwangju Military Airport relocation site on August 28, 2026.
The Honam semiconductor cluster is expected to be completed within three to four years. After the Blue House officially announced the site location, a more accelerated pace has begun. The government's "balanced development" policy aims to expand regional investment and contribute to local economic growth.
Political Controversy and Response
Political debate between ruling and opposition parties has arisen over the Honam semiconductor cluster site selection. The PPP demanded disclosure of land ownership in Honam and targeted it for special investigation, intensifying political conflict. However, the government emphasized that the "Honam Semiconductor Cluster" should be pursued as a national strategy rather than a political issue.
On July 1-2, 2026, a period of intense online debate occurred over two days, with weekend discussions dominating social media. This reflects public opinion formation around the government's investment decision.
Future Plans
The Honam semiconductor cluster aims to begin construction in July 2027, with infrastructure support policies designed to boost local economic activity. The cluster is expected to operate fully by the end of 2029 when power grid completion is scheduled.
The government aims to promote regional economic development through its non-capital region balanced development policy, with the Honam semiconductor cluster being a key project under this strategy. With Gwangju Military Airport confirmed as the site, Muan County is poised to become a new hub for regional economic growth.
Key Information to Verify
The selection of the Honam semiconductor cluster site continues to face political debate and land speculation prevention measures. While the government has officially announced the site confirmation, demands for disclosure of investment criteria and ongoing political tensions remain. The power grid is targeted for completion by the end of 2029, with infrastructure support policies intended to boost regional economic activity.
During the selection process, areas near Ramsar wetlands and Muan Mangun-myeon were among the main candidates, with a 364-square-kilometer land transaction control zone established to prevent speculation. Samsung Electronics and SK Hynix selected government-owned land near Gwangju Military Airport as their candidate site.
The Honam semiconductor cluster was based on power grid infrastructure, water supply availability, and balanced regional development policies, with the final decision being the area near Gwangju Military Airport. According to a July 6, 2026 Shin-A Ilbo report, the Blue House officially announced the site location for the Honam Semiconductor Industrial Complex as "Gwangju Military Airport."
Frequently Asked Questions
Why was Gwangju Military Airport area confirmed as the Honam semiconductor cluster site?
The Honam semiconductor cluster site selection was based on power grid infrastructure, water supply availability, and balanced regional development policies. The final decision centered on the area near Gwangju Military Airport.
When is the power grid for the Honam semiconductor cluster expected to be completed?
The Honam semiconductor cluster power grid is scheduled to be completed by the end of 2029 using ±500kV voltage HVDC and underground methods.
How is regional economic revitalization expected from the Honam semiconductor cluster?
A policy offering up to 100% support for infrastructure costs has been introduced, with the eastern part of South Jeolla Province selected as the cluster location due to its potential for regional balance and infrastructure development.
Was there controversy during the site selection process for the Honam semiconductor cluster?
Yes, political debate between ruling and opposition parties and land speculation prevention measures have continued. A 364-square-kilometer land transaction control zone was established to prevent speculation, and Representative Yu Seung-min called for public disclosure of semiconductor investment site criteria.
Frequently Asked Questions
The selection of Gwangju Military Airport area as the Honam semiconductor cluster site marks a new phase in regional economic revitalization and balanced development policies. With the government aiming to operate the cluster fully by 2029, political tensions over investment criteria transparency remain significant. The Honam semiconductor cluster has the potential to become a model for regional growth beyond just an industrial project.
After power grid completion, it is expected that the area near Gwangju Military Airport will grow into South Korea's largest semiconductor cluster. This development could significantly reshape economic dynamics in the region.
You can view similar articles on this topic all at once.
View Related ArticlesFAQ
Why was Gwangju Military Airport area confirmed as the Honam semiconductor cluster site?
The Honam semiconductor cluster site selection was based on power grid infrastructure, water supply availability, and balanced regional development policies. The final decision centered on the area near Gwangju Military Airport.
When is the power grid for the Honam semiconductor cluster expected to be completed?
The Honam semiconductor cluster power grid is scheduled to be completed by the end of 2029 using ±500kV voltage HVDC and underground methods.
How is regional economic revitalization expected from the Honam semiconductor cluster?
A policy offering up to 100% support for infrastructure costs has been introduced, with the eastern part of South Jeolla Province selected as the cluster location due to its potential for regional balance and infrastructure development.
Was there controversy during the site selection process for the Honam semiconductor cluster?
Yes, political debate between ruling and opposition parties and land speculation prevention measures have continued. A 364-square-kilometer land transaction control zone was established to prevent speculation, and Representative Yu Seung-min called for public disclosure of semiconductor investment site criteria.