Honam Semiconductor Cluster: Key Projects and Timeline Overview

Key Highlights
Total Scale and Goals of the Honam Semiconductor Cluster
The Honam Semiconductor Cluster is a large-scale project worth 80 trillion won, aiming for its first chip production by 2030. This is not just an industrial investment but a national strategy to build a semiconductor ecosystem, with 6 trillion won allocated to water infrastructure development. The project expects to create 710,000 jobs and generate 1,627 trillion won in economic benefits. The government has designated it as one of the 'three major mega projects' to accelerate its progress, exempting it from preliminary feasibility studies to expedite power and water infrastructure construction. The 80 trillion won investment focuses on strengthening global competitiveness in the semiconductor industry and enhancing domestic technological self-reliance.
Key Schedule for Power and Water Infrastructure Construction
The construction of power and water facilities for the Honam Semiconductor Cluster is scheduled to begin in July next year, aiming to complete power supply by the end of 2028. The power infrastructure will be built using an underground transmission line system, which has faced some delays compared to initial plans. To address this, the government is working to expedite progress as much as possible. Water infrastructure, also costing 6 trillion won, is essential for supporting enterprise production activities within the cluster. Since power and water infrastructure form the core foundation for semiconductor fab operations, any delay could disrupt the entire schedule, prompting close attention from both the government and relevant companies.
Government Strategy: Shifting from 'Speed Race' to 'All-Out Effort'
The president has shifted the Honam Semiconductor Cluster's direction from a 'speed race' to an 'all-out effort' to accelerate early construction. This move reflects a determination to complete foundational infrastructure within a short period, targeting completion of basic infrastructure within five years. To achieve this, the government is using Gwangju Gwangsan District's Sandeung Area as a supporting zone to speed up land acquisition and resolution of land issues, collaborating with private companies like Kangdong C&E to prioritize land transfer and development. This step is critical for achieving the 2030 chip production goal. Additionally, the government plans to strengthen tax incentives and infrastructure support to encourage corporate participation, aiming to solidify collaboration within the cluster.
Participation of Major Companies and Site Selection
Samsung Electronics and Nicks (Samsung Nicks) are carefully reviewing specific locations for their facilities, which will significantly impact the cluster's success. SK Hynix executives recently visited Gwangju Gung Airport to inspect progress on Honam semiconductor fab construction, with active participation from related companies expected to continue. SK Hynix is developing concrete plans for fab construction to strengthen collaboration within the cluster. Samsung and Nicks are expected to finalize their site selections by the first half of 2027, which will lay the groundwork for the first fab construction in the cluster. Samsung Electronics is also expected to choose an optimal location within Gwangju and Jeollanam-do based on connections with existing semiconductor production facilities.
Gwangju Gwangsan District Sandeung Area: Role as a Supporting Zone
The Gwangju Gwangsan District Sandeung Area will serve as the supporting zone for the Honam Semiconductor Cluster, playing a key role in resolving land issues. After Park Pil-soon, a former member of the Jeollanam-do Provincial Council, proposed Sandeung Area as the Honam semiconductor support area on September 7, 2026, Kangdong C&E began prioritizing land transfer and development. This helps quickly resolve site acquisition issues for companies, contributing to achieving the 2030 chip production goal. The development of Sandeung Area focuses not only on providing land but also on supporting smooth logistics and workforce movement within the cluster, aiming to maximize industrial agglomeration effects while boosting local economic activity.
Upcoming Schedule and Key Points for Readers
The key schedule for the Honam Semiconductor Cluster includes: construction of power and water facilities in July next year, completion of power supply by end of 2028, first phase of Honam semiconductor fab completion in 2029, and first chip production by 2030. Readers should monitor this schedule closely, especially the specific site decisions by Samsung Electronics and Nicks, and changes in government support policies. It is also important to confirm whether power and water infrastructure construction proceeds as planned. On August 10, 2027, President Yoon and Samsung Nicks will jointly hold a national announcement meeting to publicly share cluster plans, aiming to gain public understanding and support through transparent information sharing. Readers are advised to follow these schedules to monitor the progress of the cluster.
FAQ
What is the scale of the Honam Semiconductor Cluster?
The project is worth 80 trillion won, aiming for its first chip production by 2030.
What are the key schedules for power and water infrastructure construction?
Construction is scheduled to begin in July next year, targeting completion of power supply by the end of 2028.
What role does Gwangju Gwangsan District Sandeung Area play?
The area serves as a supporting zone for the Honam Semiconductor Cluster and plays an important role in resolving land issues.
You can find similar articles all at once here.
View Related ArticlesFAQ
What is the scale of the Honam Semiconductor Cluster?
The project is worth 80 trillion won, aiming for its first chip production by 2030.
What are the key schedules for power and water infrastructure construction?
Construction is scheduled to begin in July next year, targeting completion of power supply by the end of 2028.
What role does Gwangju Gwangsan District Sandeung Area play?
The area serves as a supporting zone for the Honam Semiconductor Cluster and plays an important role in resolving land issues.
Korean Source
This article is an English localization of a Korean-language report from BlogScore. Original: 호남 반도체 클러스터 주요 사업 계획과 구체적 추진 일정